(September 2024) Traffic counts completed in August.  

(August 2024) Field surveying is underway.  

(January 2024) The city is in the process of contracting with an engineering firm to begin developing the final design later this spring. 

(June 2023) Dunwoody was awarded federal funds to construct Phase II of the path and is beginning work on the design plans.

tiimeline showing project in concept phase

Project Information

The Winters Chapel Path project arose out of a  joint study, “Peachtree Corners – Dunwoody: Winters Chapel Road Area Study,” which was adopted by both cities in April 2015.  Phase II of the path extends along the west side of Winters Chapel Road from the end of Phase I at Charmant Place southward to Peeler Road with a section of the path passing through Peachtree Corners. The design is for a 12-foot wide concrete path for two-way bicycle and pedestrian traffic that is separated from the roadway by a landscaped buffer.  Decorative pedestrian lights are also proposed.     

Previous Project Activities

Phase I from Dunwoody Club Drive to Charmant Place is scheduled to be completed in July 2023.

Winters Chapel Typical Section