Public Works

Mount Vernon Road at Vermack Road/Manhasset Drive

The intersection at Mount Vernon Road and Vermack Road/Manhasset Drive has been identified in the City of Dunwoody’s Comprehensive Transportation Plan as a high priority project due to its current poor level of service. Mount Vernon Road is one of the primary east-west corridors in the city and Vermack Road provides access to Dunwoody High School and Vanderlyn Elementary School.

The current intersection is signalized; however, the lack of turn lanes causes long traffic queues and excessive wait times. The intersection is also deficient in accommodating bicyclists and pedestrians.  This project aims to provide a solution for the traffic congestion and to accommodate mobility and safety for vehicles, pedestrians and bicyclists.

After presentation of four options at a public meeting, followed by direction from the City Council, Alternative 1C was selected as the final design.  The resultant intersection improvements will improve the safety for vehicles and pedestrians.  Additionally, this improvement will respect and maintain the character of the surrounding existing neighborhoods and minimize impacts to property owners.

Current Project Phase –  Construction

The project is currently entering the final stages of completion. Final earthwork, concrete curb and sidewalk construction will be occuring over the next few months.

March 2019
April 2019
July 2019
RECENT PROJECT UPDATES

Spring 2019 - Utility work completed. Final earthwork, curb and sidewalk construction continuing.

Summer 2018 - Utility relocation and construction work is underway. Summer work hour lane closures and restrictions will take place week days from 9:00 a.m. to 4:00 p.m. After Monday, August 6th when school is back in session, lane closures are limited to the hours of 9:00 a.m. to 3:00 p.m. All project work is dependent upon optimal weather conditions and generally site work will occur weekdays.

Winter 2018 - Beginning the week of February 5th construction crews will start removing trees identified within the construction area in order to relocate utilities in the area. All work is subject to favorable weather conditions and initial tree clearing activities are expected to last about three to four weeks. 

Summer 2016 - Right of way acquisition is proceeding.

Fall 2014 - Staff began the selection process to hire the consultant to aid in acquiring the needed right-of-way.

Spring 2014 - The project consultant completed the design work for Alternative 1C.

September 4, 2013 - After discussion of benefits and challenges, the Council directed staff to move forward with Alternative 1C which extends the limits of the project but does not extend the center turn lane to Vernon Oaks and builds around the existing utilities.

June 17, 2013 - A public meeting was held to discuss four alternatives. 

PROJECT DOCUMENTS

Alternative 1C

Contact

David Ayers
Construction Management
678-382-6854
david.ayers@dunwoodyga.gov